QEW Improvements and Widening, Fort Erie Bound from east of Guelph Line to Northshore Boulevard

MTO Contract #2025-2011

Project Schedule

The following schedule outlines the timing of planned key components within each calendar year over the contract’s duration. This schedule will be updated as the project progresses.

Year 1 - 2026

  • QEW Fort Erie and Toronto-bound shoulder strengthening.

  • QEW median overpass construction at Brant Street.

  • QEW median overpass construction at CNR Corridor.

  • Widening of the highway median.

  • Other works include lighting upgrades, temporary works to facilitate construction, and traffic signals.    

Year 2 - 2027

  • QEW median overpass construction at Brant Street

  • Rehabilitation of the QEW Fort Erie overpass at Brant Street.

  • QEW median overpass construction at CNR Corridor.

  • Rehabilitation of the QEW Fort Erie overpass at CNR Corridor.

  • QEW median overpass at Fairview Street.

  • Rehabilitation of the QEW Fort Erie overpass at Fairview Street.

  • Rehabilitation of the Hwy 403/Hwy 407 ramp to Fairview structure.  

  • Widening of the highway median.

  • Other works include light upgrades, temporary work to facilitate construction, and traffic signals.   

Year 3 - 2028

  • Rehabilitation of the QEW Fort Erie overpass at Brant Street.

  • Rehabilitation of the QEW Fort Erie overpass at CNR Corridor.

  • Rehabilitation of the QEW Fort Erie overpass at Fairview Street.

Year 4 - 2029

  • Asphalt resurfacing on the QEW Fort Erie-bound.

  • Asphalt resurfacing on the Guelph Line underpass

  • Remaining highway improvement, including OHS installations.